Kammouh, O. (author), Nogal Macho, M. (author), Binnekamp, R. (author), Wolfert, A.R.M. (author)Construction project management requires dynamic mitigation control to ensure a project's timely completion. Current mitigation approaches are usually performed by an iterative Monte Carlo (MC) analysis which does not reflect (1) the project manager's goal-oriented behavior, (2) contractual project completion performance schemes, and (3)...journal article 2022
- document
-
Kammouh, O. (author), Nogal Macho, M. (author), Binnekamp, R. (author), Wolfert, A.R.M. (author)Probabilistic Monte Carlo simulations are often used to determine a project's completion time given a required probability level. During project execution, schedule changes negatively affect the probability of meeting the project's completion time. A manual trial and error approach is then conducted to find a set of mitigation measures to...journal article 2021