Searched for: subject%3A%22building%255C+pit%22
(1 - 8 of 8)
document
Bosch, J.W. (author), Broere, W. (author)
The construction of the North-South metro line project in Amsterdam (the Netherlands) is ongoing for the last five years and until recently suffered no major construction incidents. In the summer of 2008 two leakages occurred in one of the building pits of the deep stations. These leakages caused major settlement of a number of historical houses...
conference paper 2009
document
Van Seters, A.J. (author), Spendel, K.J. (author)
In The Hague, a 2 storey parking garage was built beneath a reinstated canal at the Veenkade with 160 parking places. The canal and the parking garage were installed at minimum 3 - 6 m distance from old houses with a shallow foundation by means of a 10 m deep building pit. A risk analysis was undertaken and major risks were identified, resulting...
conference paper 2015
document
Flow processes, taking place during the concreting of diaphragm wall panels (D-wall panels), are of great importance for the quality of the wall. During this phase, the bentonite, present in the excavated trench, should be completely replaced by concrete in a controlled way. In literature several cases are described in which this process...
conference paper 2015
document
Van Dalen, J.H. (author), Bosch, J.W. (author), Broere, W. (author)
Flow processes, taking place during the concreting of diaphragm wall panels (D-wall panels), are of great importance for the quality of the wall. During this phase, the bentonite, present in the excavated trench, should be completely replaced by concrete in a controlled way. In literature several cases are described in which this process...
conference paper 2015
document
Van Dalen, J.H. (author), Bosch, J.W. (author), Broere, W. (author)
Flow processes, taking place during the concreting of diaphragm wall panels (D-wall panels), are of great importance for the quality of the wall. During this phase, the bentonite, present in the excavated trench, should be completely replaced by concrete in a controlled way. In literature several cases are described in which this process...
conference paper 2015
document
van Dalen, J.H. (author), Servais, R. (author), Boone, D.C. (author)
The A2 tunnel in Maastricht has been built within a dry building pit with a maximum depth of 22 meters with sheet pile walls, suspended in a cement bentonite trench supported by struts at 2 to 4 levels. Dewatering is done by deepwells. The excavation reaches into Limestone layers so the maximum mobilized passive resistance of the sheet pile wall...
conference paper 2015
document
Meijers, P. (author)
During vibratory sheet piling quite often the soil near the sheet pile wall will settle. In many cases this is not a problem. For situations with houses, pipelines, roads or railroads at relative short distance these settlements may not be acceptable. The purpose of the research described in this thesis is to develop a model that is capable of...
doctoral thesis 2007
document
Meerten van, J.J. (author), Wit, M.S. de (author), Brassinga, H.E. (author), Stoevelaar, R. (author)
report 2003
Searched for: subject%3A%22building%255C+pit%22