Design-to-Hull Integration

Analysis and Optimization of the Engineer-to-Order Process Chain

Master Thesis (2026)
Author(s)

J. Carrera Gutierrez (TU Delft - Mechanical Engineering)

Contributor(s)

J.F.J. Pruyn – Mentor (TU Delft - Mechanical Engineering)

A. Napoleone – Graduation committee member (TU Delft - Mechanical Engineering)

Jeroen Kortenoeven – Mentor

Faculty
Mechanical Engineering
More Info
expand_more
Publication Year
2026
Language
English
Graduation Date
27-11-2026
Awarding Institution
Delft University of Technology
Programme
Marine Technology
Faculty
Mechanical Engineering
Page Views
6
Reuse Rights

Other than for strictly personal use, it is not permitted to download, forward or distribute the text or part of it, without the consent of the author(s) and/or copyright holder(s), unless the work is under an open content license such as Creative Commons.

Abstract

Building a custom superyacht means starting the hull before the engineering is finished. Somewhere between design and production, someone has to decide which unfinished parts can go ahead and which risks come with them. That decision is rarely written down. The same happens in any project where design and construction overlap.
This thesis studies that moment at Gate 4, where basic engineering (DOII) is released into detail engineering (DE) at Scheepswerf Slob, the hull yard of the Feadship group. The group’s own measurements show that only about one in three structural deliverables reaches detail engineering on time. Interviews and project records show that engineers already cope by working around unfinished areas. What is missing is a shared record of what may go ahead, under which condition and who accepts the remaining risk.
Building on existing maturity assessments (PDRI, FEED MATRS and DECRIS) and on research into working with preliminary information, the thesis designs GAIA, the Gate Assessment of Information Availability. GAIA checks the context of a delivery, rates how mature each discipline is and turns every open item into one of four recorded decisions: GO, CONDITIONAL, ISOLATE or WAIT. It works with the lists and meetings that already exist.
GAIA was applied to three completed deliveries. What it would have decided at the gate was compared with what happened afterwards and other explanations were checked. Several items it would have held back or put under a condition were followed by changes or extra work in the same place. The context check also flagged a risk that no open item showed: a pending vibration result. Other problems had causes outside the design information, such as designs that were hard to build.
GAIA does not predict rework. It offers a way to make expert judgement visible and traceable, without replacing it. How much time and money that saves can only be seen in practice.