Concrete Flow in Diaphragm Wall Panels

A Full-Scale In-Situ Test

More Info
expand_more

Abstract

Flow processes, taking place during the concreting of diaphragm wall panels (D-wall panels), are of great importance for the quality of the wall. During this phase, the bentonite, present in the excavated trench, should be completely replaced by concrete in a controlled way. In literature several cases are described in which this process resulted in bentonite inclusions in the panel. These inclusions often lead to severe problems, like leakages, for the building pit to be excavated within the diaphragm wall panels. Beside the risks for the building pit, leakages caused by bentonite inclusions can also have large consequences for nearby constructions. In this article, set up and results of a full-scale diaphragm wall test are described. Conclusions are drawn with regard to the influence of several parameters on the flow process and subsequently on the quality of the wall and the risk on bentonite inclusions.