Using priority-rules to guide constraint solvers

This paper introduces a new approach to the Preemptive Resource Constrained Project Scheduling Problem with setup times. The method makes use of a Constraint Optimization Problem solver, which has been modified to use priority-rule-based heuristics in its variable and value selection procedures. An alternative implementation which uses a combination of a priority-rule heuristic and a domain-independent solver heuristic has also been investigated. Both methods were tested on four well-known problem sets against a problem-independent solver configuration. Experimental results show a significant reduction in the time needed to find optimal solutions for the new methods. ...