Kammouh, O. (author), Kok, M.W.A. (author), Nogal Macho, M. (author), Binnekamp, R. (author), Wolfert, A.R.M. (author)Changes in a construction project schedule can impact the project's planned duration, resulting in penalties. A manual trial-and-error probabilistic approach is usually conducted to find an appropriate set of corrective measures to mitigate delays of the overall project. However, this approach does not capture the actual goal-oriented...journal article 2022
- document
-
Kammouh, O. (author), Nogal Macho, M. (author), Binnekamp, R. (author), Wolfert, A.R.M. (author)Probabilistic Monte Carlo simulations are often used to determine a project's completion time given a required probability level. During project execution, schedule changes negatively affect the probability of meeting the project's completion time. A manual trial and error approach is then conducted to find a set of mitigation measures to...journal article 2021