P.G.F. Sliggers
Please Note
15 records found
1
The objective of this research is to gain insight into the modelling approach and the magnitude of EAC movements and investigate how they can most efficiently be minimized. This is achieved by investigating three phases: 1) simulating a number of load cases on a global jacket model and extracting interface forces near the seabed, 2) using these interface forces to assess the EAC movement on a detailed pile-leg reference model with a full circular stopper 3) analysing this reference stopper by testing three modified configurations. These configurations are designed with respectively two, three and four brackets yielding the same contact area. A sensitivity study is then performed by increasing the contact area.
The largest EAC movement within all models can be measured at the tip of the jacket leg. The location of this movement on the circumference of the leg varies based on the loading condition and stopper model. In general simulations on the reference model showed EAC movements below 1 mm due to a uniform stress distribution from the stopper to the foundation pile. For larger wave loads, sliding occurred resulting in large EAC movements. The initial modified configurations show significantly larger EAC movement when compared to the reference stopper. In general, the EAC movement decrease when the number of brackets increases. This is the result of a more even stress distribution around the circumference of the pile. A phenomenon visible for the two bracket stopper is rotation around the axis of the wave direction resulting in large EAC movement. This effect, denoted as moment induced rotations, should be limited by all means. A sensitivity analysis on friction showed that sliding could most efficiently be solved by increasing the friction coefficient. This is highly recommended since it greatly improves the performance of the stopper connection for larger waves.
This research could be further extended by performing a large sensitivity study to normalize the current results. This would be needed to verify whether the current conclusions can also be adopted for general use. ...
The objective of this research is to gain insight into the modelling approach and the magnitude of EAC movements and investigate how they can most efficiently be minimized. This is achieved by investigating three phases: 1) simulating a number of load cases on a global jacket model and extracting interface forces near the seabed, 2) using these interface forces to assess the EAC movement on a detailed pile-leg reference model with a full circular stopper 3) analysing this reference stopper by testing three modified configurations. These configurations are designed with respectively two, three and four brackets yielding the same contact area. A sensitivity study is then performed by increasing the contact area.
The largest EAC movement within all models can be measured at the tip of the jacket leg. The location of this movement on the circumference of the leg varies based on the loading condition and stopper model. In general simulations on the reference model showed EAC movements below 1 mm due to a uniform stress distribution from the stopper to the foundation pile. For larger wave loads, sliding occurred resulting in large EAC movements. The initial modified configurations show significantly larger EAC movement when compared to the reference stopper. In general, the EAC movement decrease when the number of brackets increases. This is the result of a more even stress distribution around the circumference of the pile. A phenomenon visible for the two bracket stopper is rotation around the axis of the wave direction resulting in large EAC movement. This effect, denoted as moment induced rotations, should be limited by all means. A sensitivity analysis on friction showed that sliding could most efficiently be solved by increasing the friction coefficient. This is highly recommended since it greatly improves the performance of the stopper connection for larger waves.
This research could be further extended by performing a large sensitivity study to normalize the current results. This would be needed to verify whether the current conclusions can also be adopted for general use.
An analysis of a deep-sea mining nodule mining system
Vertical transportation by means of mechanical lifting
Feasibility of a marginal offshore development in the Guyana-Suriname Basin
A study on the technical and economic feasibility of development of a marginal oil reservoir in the Guyana-Suriname Basin in the shallow areas offshore Suriname
The objective of this study is to propose a framework for reassessing existing OWT support structures for lifetime extension since there is not a clear detailed methodology describing the assessment and extension which can be applied for OWT support structures. Because of the complexity of the problem and the limited time, only the governing limit state is studied which is the fatigue limit state. The proposed framework consists of two phases. The first phase is the reassessment phase in which the available documentation and measurements of the (operational) history are taken into account to determine the fatigue damage with more certainty from the installation of the OWT till the point when the reassessment takes place. The second phase is the remaining useful lifetime (RUL) prediction phase, which aims at determining the remaining operational lifetime of an OWT without exceeding the safety limits. For both phases, different methods can be used that can be classified in deterministic methods and probabilistic methods. Finally, the suggested framework is demonstrated in a simplified case study. First, the fatigue lifetime of the simplified structure is calculated with wave conditions of the Gemini wind farm; This calculated lifetime resembles the initial design lifetime and serves as a comparative measure for the following reassessment and RUL prediction phases. Then the simplified structure is reassessed with updated data, using a deterministic method. Subsequently, the RUL is predicted by using probabilistic fatigue calculations whereby different uncertainty distributions are taken into account. From this case study, it can be concluded that the proposed framework is applicable for different amounts and types of measurement data as well as assessment methods. The deterministic reassessment shows different outcomes of fatigue life of the structure even with a small change in the input parameters. The probabilistic fatigue calculations used for the RUL are computational more complicated but very promising since site-specific uncertainty distributions replace the generalized partial safety factors. The suggestion is, therefore, to use probabilistic models to achieve a longer lifetime for the OWT support structure without compromising the safety levels. ...
The objective of this study is to propose a framework for reassessing existing OWT support structures for lifetime extension since there is not a clear detailed methodology describing the assessment and extension which can be applied for OWT support structures. Because of the complexity of the problem and the limited time, only the governing limit state is studied which is the fatigue limit state. The proposed framework consists of two phases. The first phase is the reassessment phase in which the available documentation and measurements of the (operational) history are taken into account to determine the fatigue damage with more certainty from the installation of the OWT till the point when the reassessment takes place. The second phase is the remaining useful lifetime (RUL) prediction phase, which aims at determining the remaining operational lifetime of an OWT without exceeding the safety limits. For both phases, different methods can be used that can be classified in deterministic methods and probabilistic methods. Finally, the suggested framework is demonstrated in a simplified case study. First, the fatigue lifetime of the simplified structure is calculated with wave conditions of the Gemini wind farm; This calculated lifetime resembles the initial design lifetime and serves as a comparative measure for the following reassessment and RUL prediction phases. Then the simplified structure is reassessed with updated data, using a deterministic method. Subsequently, the RUL is predicted by using probabilistic fatigue calculations whereby different uncertainty distributions are taken into account. From this case study, it can be concluded that the proposed framework is applicable for different amounts and types of measurement data as well as assessment methods. The deterministic reassessment shows different outcomes of fatigue life of the structure even with a small change in the input parameters. The probabilistic fatigue calculations used for the RUL are computational more complicated but very promising since site-specific uncertainty distributions replace the generalized partial safety factors. The suggestion is, therefore, to use probabilistic models to achieve a longer lifetime for the OWT support structure without compromising the safety levels.
Such a bridge should be able to follow the excitations that are imposed at its two ends from the response of the connected platforms due to the applied environmental loads. Thus, in its longitudinal direction, the bridge should be pinned-supported at one platform and sliding-supported at the other. Such a configuration enables the bridge to adapt to the continuously varying relative movement that is induced by the motion of the two connected platforms. This results in the generation of friction at the sliding end of the bridge.
Similarly to any other offshore structure, a bridge landing should be able to withstand the maximum operating loads and its configuration should be checked against the different limit states. Although a jacket substructure is commonly analysed against the serviceability, ultimate and fatigue limit states, a bridge landing is checked against only the first two states. However, the generated friction at the sliding bridge supports results in varying stresses at the corresponding bridge landing. This indicates that the fatigue limit state should also be examined and thus investigation is required in order to highlight its significance in the design of such a structure.
This is the motivation behind the certain thesis, which intends to clarify the sensitivity of a bridge landing into the varying dynamic load of the generated friction. In order to do so, a specific case is examined, with real information about the structure and the environmental details. The analysis comprises examining three limit states (SLS, ULS, FLS), concluding into the governing one for the case of the bridge landing. The structural analyses were performed using the SACS software, which enables performing all the SLS and ULS checks. Regarding fatigue, though, the whole analysis was conducted independently, using a simplified approach that enables to deal with the issue in a quick way. This comprises the base case approach, through which assumptions are made regarding the wave and friction main characteristics.
After verifying the significance of the fatigue limit state in the design, an assessment of the base case approach follows. This is performed through the examination of the main sensitivity parameters that influence the simplified approach through which the fatigue assessment was conducted. The results of the sensitivity analyses are then incorporated in order to review the method and conclude into any possible improvements.
Finally, enhancement of the structure is examined through four different ways, aiming to turn it to be sufficient against the fatigue requirements. The improvement actions consist of improving the existing weld details, modifying the existing structure and reinforcing of members.
It should be noted that the problem was also approached through a numerical approach that was generated using the Matlab software. Through this, it was intended to capture the behaviour of friction in a more realistic way before incorporating it in the fatigue assessment, something that was not possible to be done inside SACS. However, the model didn’t show rational results and thus it could not be used in the fatigue analysis. The whole procedure and theory, though, are described in detail since it is possible that they can set a useful background for further investigation. ...
Such a bridge should be able to follow the excitations that are imposed at its two ends from the response of the connected platforms due to the applied environmental loads. Thus, in its longitudinal direction, the bridge should be pinned-supported at one platform and sliding-supported at the other. Such a configuration enables the bridge to adapt to the continuously varying relative movement that is induced by the motion of the two connected platforms. This results in the generation of friction at the sliding end of the bridge.
Similarly to any other offshore structure, a bridge landing should be able to withstand the maximum operating loads and its configuration should be checked against the different limit states. Although a jacket substructure is commonly analysed against the serviceability, ultimate and fatigue limit states, a bridge landing is checked against only the first two states. However, the generated friction at the sliding bridge supports results in varying stresses at the corresponding bridge landing. This indicates that the fatigue limit state should also be examined and thus investigation is required in order to highlight its significance in the design of such a structure.
This is the motivation behind the certain thesis, which intends to clarify the sensitivity of a bridge landing into the varying dynamic load of the generated friction. In order to do so, a specific case is examined, with real information about the structure and the environmental details. The analysis comprises examining three limit states (SLS, ULS, FLS), concluding into the governing one for the case of the bridge landing. The structural analyses were performed using the SACS software, which enables performing all the SLS and ULS checks. Regarding fatigue, though, the whole analysis was conducted independently, using a simplified approach that enables to deal with the issue in a quick way. This comprises the base case approach, through which assumptions are made regarding the wave and friction main characteristics.
After verifying the significance of the fatigue limit state in the design, an assessment of the base case approach follows. This is performed through the examination of the main sensitivity parameters that influence the simplified approach through which the fatigue assessment was conducted. The results of the sensitivity analyses are then incorporated in order to review the method and conclude into any possible improvements.
Finally, enhancement of the structure is examined through four different ways, aiming to turn it to be sufficient against the fatigue requirements. The improvement actions consist of improving the existing weld details, modifying the existing structure and reinforcing of members.
It should be noted that the problem was also approached through a numerical approach that was generated using the Matlab software. Through this, it was intended to capture the behaviour of friction in a more realistic way before incorporating it in the fatigue assessment, something that was not possible to be done inside SACS. However, the model didn’t show rational results and thus it could not be used in the fatigue analysis. The whole procedure and theory, though, are described in detail since it is possible that they can set a useful background for further investigation.
Design optimization of an adjustable Pre-Piling-Template
For wind-turbine installation
This thesis aims to analyze the adjustability of the Pre-Piling Template for windturbine installation based on quasi-static calculations.
First a number of conceptual designs of a versatile adjustable Pre-Pilling Template are made. A wide variety of configurations is configured. The complicated part of the design is that the Pre-Piling Template must be viable for a three-legged and four-legged configurations with several centre-to-centre distances. Thereby, it should be possible to convert the entire system on deck of a vessel during given offshore conditions. From eleven concepts a selection of two alternatives has been made, based on listed criteria by the client: Robustness, Adjustability, Financial costs and Safety.
For two selected cross-centre alternatives a global structural analysis is performed under environmental loading. One cross-centre is a composed cross centre, with which a three- and four-legged configuration can be installed with the same cross-centre mid-frame of the PPT. The other alternative consist of two separate mid-frames, one for a three- and one for a four-legged configuration. To speed up the installation process, primarily all the piles to be installed will be stabbed into the Pre-Piling Template. After all piles have been stabbed into the frame, the hammering procedure will start. When all piles are stabbed significant forces arises from wind and especially hydrodynamic actions. The static deformations of the template induced during the multiple installation steps can cause overall displacements of the centre of each particular sleeve.
The added value of a Pre-Piling Template is the installation speed versus the required accuracy of the pile installation. A high installation speed only makes sense if piles can be installed within the required tolerances. Therefore the deformations of the frame and the corresponding displacements are governing. To determine the displacements, a 3D-model is constructed and a rotational and translational spring is implemented to model the soil-structure interaction. To consider this soil-structure interaction, a model by A.B. Cammaert et al (2011) is used to determine the required stiffnesses. The model is modelled using Matrix Frame software, with which the final displacements, at the height of the mid-frame, have been determined.
A detailed analysis of the static internal forces is worked out based on a bolted flange-flange connection. Checks are done conform Det Norske Veritas (2010) and based on a ULS-driven design. Two potential connection configurations are worked out; an alternative with less but more heavy bolts of M64, as well as an alternative with substantial more smaller bolts of M36.
Finally, several optimisations are identified to speed up the installation time of assembling and disassembling the adjustable Pre-Piling Template. Recommendations are made in cooperation with Breman Machinery and will result, in consultation with installation experts that are well known with the barge of the client, to a final design.
A clear conclusion, about the PPT-design, can not be made because the installation is site specific. If a project includes two different configurations, a three- and four-legged foundation design, a composed mid-frame that is viable for both configurations is recommended. For this composed mid-frame variant the operation to adjust the frame to another footprint can be done more efficient with a higher safety level on deck of the vessel.
...
This thesis aims to analyze the adjustability of the Pre-Piling Template for windturbine installation based on quasi-static calculations.
First a number of conceptual designs of a versatile adjustable Pre-Pilling Template are made. A wide variety of configurations is configured. The complicated part of the design is that the Pre-Piling Template must be viable for a three-legged and four-legged configurations with several centre-to-centre distances. Thereby, it should be possible to convert the entire system on deck of a vessel during given offshore conditions. From eleven concepts a selection of two alternatives has been made, based on listed criteria by the client: Robustness, Adjustability, Financial costs and Safety.
For two selected cross-centre alternatives a global structural analysis is performed under environmental loading. One cross-centre is a composed cross centre, with which a three- and four-legged configuration can be installed with the same cross-centre mid-frame of the PPT. The other alternative consist of two separate mid-frames, one for a three- and one for a four-legged configuration. To speed up the installation process, primarily all the piles to be installed will be stabbed into the Pre-Piling Template. After all piles have been stabbed into the frame, the hammering procedure will start. When all piles are stabbed significant forces arises from wind and especially hydrodynamic actions. The static deformations of the template induced during the multiple installation steps can cause overall displacements of the centre of each particular sleeve.
The added value of a Pre-Piling Template is the installation speed versus the required accuracy of the pile installation. A high installation speed only makes sense if piles can be installed within the required tolerances. Therefore the deformations of the frame and the corresponding displacements are governing. To determine the displacements, a 3D-model is constructed and a rotational and translational spring is implemented to model the soil-structure interaction. To consider this soil-structure interaction, a model by A.B. Cammaert et al (2011) is used to determine the required stiffnesses. The model is modelled using Matrix Frame software, with which the final displacements, at the height of the mid-frame, have been determined.
A detailed analysis of the static internal forces is worked out based on a bolted flange-flange connection. Checks are done conform Det Norske Veritas (2010) and based on a ULS-driven design. Two potential connection configurations are worked out; an alternative with less but more heavy bolts of M64, as well as an alternative with substantial more smaller bolts of M36.
Finally, several optimisations are identified to speed up the installation time of assembling and disassembling the adjustable Pre-Piling Template. Recommendations are made in cooperation with Breman Machinery and will result, in consultation with installation experts that are well known with the barge of the client, to a final design.
A clear conclusion, about the PPT-design, can not be made because the installation is site specific. If a project includes two different configurations, a three- and four-legged foundation design, a composed mid-frame that is viable for both configurations is recommended. For this composed mid-frame variant the operation to adjust the frame to another footprint can be done more efficient with a higher safety level on deck of the vessel.
Structural Performance of a 10MW Turbine in Offshore Hurricane Wind Conditions
A Case Study for the Gulf of Mexico
The Jack-up frame
A novel installation method for large offshore wind turbines
The characteristics of these large size turbines were studied by examining the relation between the rated power and the rotor diameter of operating offshore wind turbines. The derived dependencies between the desired power and the required area of the rotor were validated with data from announced turbines. Extrapolating these dependencies has resulted in a prediction for the 20MW turbine of a rotor diameter of 250 metres, a hub height of 160 metres above sea level and a nacelle with a mass of around 1100 tonnes.
To be able to develop new concepts for the installation of these turbines, interviews were conducted with industry experts and criteria were derived. Next, upscaling of the equipment of the current jack-up vessel was investigated, already existing concepts were reviewed and new concepts were developed. Based on the set criteria, a suitable installation concept was chosen.
The chosen concept eliminates the need for lifting the heaviest component (the nacelle) to the highest height (hub height) by dividing the tower of the turbine into several segments. It consists of a temporary installation frame that can be placed from a jack-up vessel on top of the foundation of an offshore wind turbine. While installing the frame on the foundation with a crane, the nacelle, hub and blades are mounted together on the deck of the jack-up vessel, forming the rotor nacelle assembly (RNA). Then, the RNA together with the first segment of the tower is placed in the frame, skidded sideways and brought up by a built-in jacking mechanism in the frame. It needs to be brought up 45 metres, so the following segment of 40 metres can be skidded underneath. While jacking the first segment, the following segment is placed next to the lift frame and prepared to be skidded. After the skidding of the next segment is finished, the previous segment is lowered on top of the other segment and they are mounted together. While fastening the connection, the jacking mechanism is lowered by recycling the strokes so it can start lifting the next segment. This is repeated until the complete turbine has been installed. When all the tower segments are installed, the turbine can be commissioned and the frame is retrieved.
Optimisation of the concept has been performed by highlighting the logistical process regarding placement of the frame, lifting of the turbine and retrieval of the frame. A concept design is presented that can install the future offshore wind turbines with a rated power of up to 20MW. It is able to install the large size turbines faster compared to upscaling the existing installation equipment, it can be used for several turbine sizes and it only requires small modifications on the design of an offshore wind turbine.
The concept consists of a jack-up vessel from where the installation is performed offshore. This was preferred over a floating vessel, since movement of the jack-up vessel is reduced significantly when lifted out of the water. For wider applicability of the developed concept, for example on a free floating vessel, (non jack-up), further research is required to reduce motions between the turbine and the foundation.
...
The characteristics of these large size turbines were studied by examining the relation between the rated power and the rotor diameter of operating offshore wind turbines. The derived dependencies between the desired power and the required area of the rotor were validated with data from announced turbines. Extrapolating these dependencies has resulted in a prediction for the 20MW turbine of a rotor diameter of 250 metres, a hub height of 160 metres above sea level and a nacelle with a mass of around 1100 tonnes.
To be able to develop new concepts for the installation of these turbines, interviews were conducted with industry experts and criteria were derived. Next, upscaling of the equipment of the current jack-up vessel was investigated, already existing concepts were reviewed and new concepts were developed. Based on the set criteria, a suitable installation concept was chosen.
The chosen concept eliminates the need for lifting the heaviest component (the nacelle) to the highest height (hub height) by dividing the tower of the turbine into several segments. It consists of a temporary installation frame that can be placed from a jack-up vessel on top of the foundation of an offshore wind turbine. While installing the frame on the foundation with a crane, the nacelle, hub and blades are mounted together on the deck of the jack-up vessel, forming the rotor nacelle assembly (RNA). Then, the RNA together with the first segment of the tower is placed in the frame, skidded sideways and brought up by a built-in jacking mechanism in the frame. It needs to be brought up 45 metres, so the following segment of 40 metres can be skidded underneath. While jacking the first segment, the following segment is placed next to the lift frame and prepared to be skidded. After the skidding of the next segment is finished, the previous segment is lowered on top of the other segment and they are mounted together. While fastening the connection, the jacking mechanism is lowered by recycling the strokes so it can start lifting the next segment. This is repeated until the complete turbine has been installed. When all the tower segments are installed, the turbine can be commissioned and the frame is retrieved.
Optimisation of the concept has been performed by highlighting the logistical process regarding placement of the frame, lifting of the turbine and retrieval of the frame. A concept design is presented that can install the future offshore wind turbines with a rated power of up to 20MW. It is able to install the large size turbines faster compared to upscaling the existing installation equipment, it can be used for several turbine sizes and it only requires small modifications on the design of an offshore wind turbine.
The concept consists of a jack-up vessel from where the installation is performed offshore. This was preferred over a floating vessel, since movement of the jack-up vessel is reduced significantly when lifted out of the water. For wider applicability of the developed concept, for example on a free floating vessel, (non jack-up), further research is required to reduce motions between the turbine and the foundation.
Maintenance Offshore Wind
Feasibility study into alternative lifting systems for offshore wind turbine maintenance operations
Currently the replacement of these components is performed by a jack-up crane vessel which has two downsides: (1) long mobilization time and (2) high operational costs. The development of systems that can replace heavy components can contribute to reduce the maintenance costs of offshore wind turbines.
Therefore in the first part of this thesis, developments and techniques were investigated which can do so. It was observed that different types of solutions are already available for onshore maintenance purposes like the crane developed by Liftra and the Gamesa flexifit. Furthermore new concepts are being developed by the wind turbine manufacturer Vestas and Anson, a Chinese crane builder. These developments are addressing the problem of reducing the maintenance costs, but still two important downsides are present: (1) insufficient lifting capacity for gearbox replacement and (2) most systems are designed to be used on specific turbines.
The current developments and available techniques were studied to generate concepts that can address these shortcomings. This resulted in a promising solution where a relatively small crane is installed on the wind turbine tower from a floating vessel. A great advantage over currently used method is that no specialised maintenance vessel is required for a gearbox replacement and thereby costs and time can be saved.
This crane is attached to the tower structure by use of a clamping mechanism and is kept in position by generating frictional force. To generate this force, hydraulic cylinders are pressing the pads (contact surfaces of the clamp) against the tower structure. For the applicability of this concept it is of major importance that the structural integrity of the tower is maintained, while sufficient frictional force is generated to avoid the crane from slipping down during lifting operations. Therefore, in the second part of this thesis a feasibility study is done on the application of this clamping mechanism on wind turbine towers. By use of finite element modelling a workable contact surface configuration of this clamping mechanism was found.
The following four variables were studied: (1) elasticity of the contact layer, (2) number of pads used, (3) width and (4) height of the pads. The latter three relate to the contact surface area and the elasticity of the contact layer influences the distribution of the forces from the clamp to the tower structure.
Investigating these variables, it was concluded that; the proposed solution should have a contact layer where the elasticity modulus is higher than 1200 Mpa. By adding more pads, the loading capacity increases. However, it also results in a more complex structure and therefore it is advised to reduce the number of pads and instead widen them. Considering this trade off, a four pad configuration is selected to determine the required width and height of the pad. For this set-up it is advised to use a pad width of eighty degrees and pad height of three meter to meet the requirement of replacing the gearbox, the heaviest component of the wind turbine powertrain.
Furthermore, to assure this clamping mechanism works on towers of different dimensions (i.e. diameter and wall thickness combinations), the loading capacity was determined for a variety of tower dimensions. By doing so, insights are gathered on the application of this clamping mechanism on different turbines. To make the data useful for further application, tables are included which indicate the loading capacity for investigated wind turbine towers.
...
Currently the replacement of these components is performed by a jack-up crane vessel which has two downsides: (1) long mobilization time and (2) high operational costs. The development of systems that can replace heavy components can contribute to reduce the maintenance costs of offshore wind turbines.
Therefore in the first part of this thesis, developments and techniques were investigated which can do so. It was observed that different types of solutions are already available for onshore maintenance purposes like the crane developed by Liftra and the Gamesa flexifit. Furthermore new concepts are being developed by the wind turbine manufacturer Vestas and Anson, a Chinese crane builder. These developments are addressing the problem of reducing the maintenance costs, but still two important downsides are present: (1) insufficient lifting capacity for gearbox replacement and (2) most systems are designed to be used on specific turbines.
The current developments and available techniques were studied to generate concepts that can address these shortcomings. This resulted in a promising solution where a relatively small crane is installed on the wind turbine tower from a floating vessel. A great advantage over currently used method is that no specialised maintenance vessel is required for a gearbox replacement and thereby costs and time can be saved.
This crane is attached to the tower structure by use of a clamping mechanism and is kept in position by generating frictional force. To generate this force, hydraulic cylinders are pressing the pads (contact surfaces of the clamp) against the tower structure. For the applicability of this concept it is of major importance that the structural integrity of the tower is maintained, while sufficient frictional force is generated to avoid the crane from slipping down during lifting operations. Therefore, in the second part of this thesis a feasibility study is done on the application of this clamping mechanism on wind turbine towers. By use of finite element modelling a workable contact surface configuration of this clamping mechanism was found.
The following four variables were studied: (1) elasticity of the contact layer, (2) number of pads used, (3) width and (4) height of the pads. The latter three relate to the contact surface area and the elasticity of the contact layer influences the distribution of the forces from the clamp to the tower structure.
Investigating these variables, it was concluded that; the proposed solution should have a contact layer where the elasticity modulus is higher than 1200 Mpa. By adding more pads, the loading capacity increases. However, it also results in a more complex structure and therefore it is advised to reduce the number of pads and instead widen them. Considering this trade off, a four pad configuration is selected to determine the required width and height of the pad. For this set-up it is advised to use a pad width of eighty degrees and pad height of three meter to meet the requirement of replacing the gearbox, the heaviest component of the wind turbine powertrain.
Furthermore, to assure this clamping mechanism works on towers of different dimensions (i.e. diameter and wall thickness combinations), the loading capacity was determined for a variety of tower dimensions. By doing so, insights are gathered on the application of this clamping mechanism on different turbines. To make the data useful for further application, tables are included which indicate the loading capacity for investigated wind turbine towers.
Accelerated pipeline degradation
An approach using galvanic corrosion as contribution to offshore pipeline decommissioning
The Modular Execution Strategy aims at relocating parts of fabrication and assembly activities of a pipe rack construction to potentially low cost locations at which the conditions for fabrication and assembly activities are more favorable. The pre-assembled pipe racks will be transported to the onshore installation site by a vessel, which results in sea-transport design requirements (due to vessel motions) in addition to the in-place design.
Three options of different configuration for MES were considered. The first option is to transport only upper parts of the pipe racks without their bottom columns and assemble the bottom columns at the installation site. The second option is to transport the complete pipe racks including bottom columns which are stiffened by temporary bracings. The last option is to transport complete pipe racks with strengthened columns having a larger profile dimensions.
In order to consider various sizes of pipe racks, 27-representative configurations of pipe racks of the project were selected. These pipe racks were designed to withstand in-place loadings and sea-transport loadings with a quasi-static analysis method. The in-place loadings are weight of pipe lines and wind force. The sea-transport loadings are forces due to motions of a vessel and critical sea-transport loadings come from roll + heave and pitch + heave. Quantities of steel for each option were found after completion of the design. Subsequently, the quantities were translated into steel work cost which includes procurement, fabrication, assembly and installation costs of steel work.
As a conclusion, it was found that considering the quantities and costs of steel work for the project, option 1 (transport the pipe racks without columns) is the most cost effective solution. If pinned supports are used at the vessel deck, which are more favorable for the company, it was calculated that option 1 requires, on average, 15% and 30% less cost than option 2 and option 3 respectively. For clamped supported conditions, option 1 still requires 15% less cost than both option 2 and option 3.
Furthermore, it was demonstrated by performing a resonance check and a dynamic analysis for a tall two-dimensional frame, that a quasi-static analysis method could be used to assess the sea-transport loadings. It was found that there is very low possibility of resonance and only low dynamic amplification.
In this thesis, the focus has been on differences in the structural configurations. Other aspects, some of which may be difficult to express in cost terms such as logistical difficulty, safety/risk, and project schedule, were not taken into account. Therefore, in order to verify the attractiveness of each option in more detail, it is suggested to also make a complete assessment of those mentioned aspects.
...
The Modular Execution Strategy aims at relocating parts of fabrication and assembly activities of a pipe rack construction to potentially low cost locations at which the conditions for fabrication and assembly activities are more favorable. The pre-assembled pipe racks will be transported to the onshore installation site by a vessel, which results in sea-transport design requirements (due to vessel motions) in addition to the in-place design.
Three options of different configuration for MES were considered. The first option is to transport only upper parts of the pipe racks without their bottom columns and assemble the bottom columns at the installation site. The second option is to transport the complete pipe racks including bottom columns which are stiffened by temporary bracings. The last option is to transport complete pipe racks with strengthened columns having a larger profile dimensions.
In order to consider various sizes of pipe racks, 27-representative configurations of pipe racks of the project were selected. These pipe racks were designed to withstand in-place loadings and sea-transport loadings with a quasi-static analysis method. The in-place loadings are weight of pipe lines and wind force. The sea-transport loadings are forces due to motions of a vessel and critical sea-transport loadings come from roll + heave and pitch + heave. Quantities of steel for each option were found after completion of the design. Subsequently, the quantities were translated into steel work cost which includes procurement, fabrication, assembly and installation costs of steel work.
As a conclusion, it was found that considering the quantities and costs of steel work for the project, option 1 (transport the pipe racks without columns) is the most cost effective solution. If pinned supports are used at the vessel deck, which are more favorable for the company, it was calculated that option 1 requires, on average, 15% and 30% less cost than option 2 and option 3 respectively. For clamped supported conditions, option 1 still requires 15% less cost than both option 2 and option 3.
Furthermore, it was demonstrated by performing a resonance check and a dynamic analysis for a tall two-dimensional frame, that a quasi-static analysis method could be used to assess the sea-transport loadings. It was found that there is very low possibility of resonance and only low dynamic amplification.
In this thesis, the focus has been on differences in the structural configurations. Other aspects, some of which may be difficult to express in cost terms such as logistical difficulty, safety/risk, and project schedule, were not taken into account. Therefore, in order to verify the attractiveness of each option in more detail, it is suggested to also make a complete assessment of those mentioned aspects.
The Assessment of the Fatigue Behaviour of Offshore Wind Farm Support Structures
Dynamic Amplification of the Braces of Offshore Wind Farm Support Structures
Due to these reasons the OWTs are designed as slender constructions. When designing a structure the aim is to generate a design of which the natural frequencies do not overlap with the applied forcing frequencies. This is required to avoid resonance which results in low estimated fatigue life of the structure. A challenge regarding the slender OWT structures is that the natural frequencies are close to the forcing frequencies.
This thesis is based on a project having OWT structures with the foundation consisting of a jacket design having a framework of four bays of cross braces. During a later stage of the project it was found by the substructure designer that the structure would have a low estimated fatigue life. The cause being that the applied external forces on the structure are in the same frequency range as the natural frequency of particular cross braces in the jackets, in the range of 2 – 2.5Hz. Consequently, due to resonance large brace excitation was found in the jacket model, created by the designer, which resulted in a low expected fatigue life. To mitigate this, double sided welds and external toe grinding were implemented. However no clear explanation regarding this issue was provided and not all parties involved obtained the same results and conclusions. Therefore further investigation regarding this theoretic fatigue issue was requested.
The goal of this research is to identify and provide a clear explanation of the vibration amplification movement of the braces and thus independently assess if there is a fatigue problem with the OWT jackets. Furthermore this thesis focusses on alternative solutions to this problem, had the vibration issue been found during an earlier stage of the project.
The first part of this thesis focusses on the identification of the problem. The approach was structured in three stages;
First the identification of the forcing vibration in the critical frequency zone was performed with the use of a Fast Fourier analysis of time domain data of the applied forces on the OWT. The obtained frequency response demonstrated excitations around the critical frequency zone, which are due to the eigen-frequencies of the tower and the blades of the turbine.
This was followed by the analysis of the eigen-frequencies of the cross braces of the jacket in bay 3 and 4 for the local and global response. This was performed with the use of ANSYS modal analysis in combination with a build-up of simplified brace models. Hand calculations were performed to verify the obtained results.
Finally, a comparison was made regarding the overlapping of frequencies of the forcing frequencies and eigen-frequencies of the braces. This was done to determine if large brace amplification due to resonance would occur, resulting in a low estimated fatigue life.
The second part of this research evaluates alternative solutions to this problem. Possible concepts were elaborated with their ad- and disadvantages, followed by a multi criteria analysis. Three concepts were selected for further investigation and examined in terms of whether a successful outcome could be achieved by their implementation.
This thesis also provides a procedure with regards to identifying to the potential for resonance at an early stage of the design process. Keeping track of changes during all design phases will lead to avoiding the unexpected discovery of a short fatigue life, due to resonance, at a late design stage. ...
Due to these reasons the OWTs are designed as slender constructions. When designing a structure the aim is to generate a design of which the natural frequencies do not overlap with the applied forcing frequencies. This is required to avoid resonance which results in low estimated fatigue life of the structure. A challenge regarding the slender OWT structures is that the natural frequencies are close to the forcing frequencies.
This thesis is based on a project having OWT structures with the foundation consisting of a jacket design having a framework of four bays of cross braces. During a later stage of the project it was found by the substructure designer that the structure would have a low estimated fatigue life. The cause being that the applied external forces on the structure are in the same frequency range as the natural frequency of particular cross braces in the jackets, in the range of 2 – 2.5Hz. Consequently, due to resonance large brace excitation was found in the jacket model, created by the designer, which resulted in a low expected fatigue life. To mitigate this, double sided welds and external toe grinding were implemented. However no clear explanation regarding this issue was provided and not all parties involved obtained the same results and conclusions. Therefore further investigation regarding this theoretic fatigue issue was requested.
The goal of this research is to identify and provide a clear explanation of the vibration amplification movement of the braces and thus independently assess if there is a fatigue problem with the OWT jackets. Furthermore this thesis focusses on alternative solutions to this problem, had the vibration issue been found during an earlier stage of the project.
The first part of this thesis focusses on the identification of the problem. The approach was structured in three stages;
First the identification of the forcing vibration in the critical frequency zone was performed with the use of a Fast Fourier analysis of time domain data of the applied forces on the OWT. The obtained frequency response demonstrated excitations around the critical frequency zone, which are due to the eigen-frequencies of the tower and the blades of the turbine.
This was followed by the analysis of the eigen-frequencies of the cross braces of the jacket in bay 3 and 4 for the local and global response. This was performed with the use of ANSYS modal analysis in combination with a build-up of simplified brace models. Hand calculations were performed to verify the obtained results.
Finally, a comparison was made regarding the overlapping of frequencies of the forcing frequencies and eigen-frequencies of the braces. This was done to determine if large brace amplification due to resonance would occur, resulting in a low estimated fatigue life.
The second part of this research evaluates alternative solutions to this problem. Possible concepts were elaborated with their ad- and disadvantages, followed by a multi criteria analysis. Three concepts were selected for further investigation and examined in terms of whether a successful outcome could be achieved by their implementation.
This thesis also provides a procedure with regards to identifying to the potential for resonance at an early stage of the design process. Keeping track of changes during all design phases will lead to avoiding the unexpected discovery of a short fatigue life, due to resonance, at a late design stage.