In large modular construction projects, such as shipbuilding, multiple similar projects arrive stochastically. At project arrival, a schedule has to be created, in which future modifications are difficult and/or undesirable. Since all projects use the same set of shared resources, current scheduling decisions influence future scheduling possibilities. To model this problem, we introduce the Dynamic Resource Constrained Multi-project Scheduling Problem with Static project Schedules. To find schedules, both a greedy approach and simulation-based approach with varying scenarios are introduced. Although the simulation-based approach schedules projects proactively, the computing times are long, even for small instances. Therefore, a method is introduced that learns from schedules obtained in the simulation-based method and uses a neural network to estimate the objective function value. It is shown that this method achieves a significant improvement in objective function value over the greedy algorithm, while only requiring a fraction of the computation time of the simulation-based method.
The Resource Constrained Project Scheduling Problem with a flexible Project Structure (RCPSP-PS) is a generalization of the Resource Constrained Project Scheduling Problem (RCPSP). In the RCPSP, the goal is to determine a minimal makespan schedule subject to precedence and resource constraints. The generalization introduced in the RCPSP-PS is that, instead of executing all activities, only a subset of all activities has to be executed. We present a model that is based on two graphs: one representing precedence relations and one representing the activity selection structure. The latter defines which subset of activities has to be executed. Additionally, we present theoretical properties of this model and give an exact solution method that makes use of these properties by generating cutting planes and setting bounds on variables. Furthermore, three problem properties are introduced to classify problems in the literature. We compare our model to a model from literature on instances that possess a subset of these three problem properties and find a reduction in computing time. Furthermore, by comparing results on instances that possess all problem properties, it is shown that the computing times are decreased and better lower bounds are found by the cutting planes and variable bounds presented in this paper.
The resource constrained project scheduling problem with a flexible project structure and consumption and production of resources, involves making a selection of activities and scheduling these activities in order to minimize the makespan, subject to precedence and resource constraints. Since finding a feasible selection of activities is NP-hard, we introduce the concept of group graphs and restrict ourselves to instances with an acyclic group graph. For these instances, which represent many practical cases, we show how to make a feasible selection of activities in polynomial time and use this concept to schedule the selected activities using a hybrid differential evolution algorithm. We compare this algorithm with an algorithm from the literature on special cases of instances without consumption and production of resources, and show that our algorithm creates solutions of higher quality. Furthermore, to compare general instances, we develop an ant colony optimization algorithm that performs slightly better on special cases than the algorithm from literature and show that the hybrid differential evolution algorithm outperforms the ant colony optimization algorithm on general instances.