As lazy clause generation has seen much success in recent years, the generation of explanations has become the focus of much research. This paper describes how explanations can be generated for detectable precedences in the disjunctive constraint. We also provide a method to inco
...
Propagators for Constraint Programming Energetic Reasoning
Exploring the Effect of Explanations for Energetic Reasoning
The cumulative constraint is often used when modeling constraint programming problems, frequently seen in scheduling and planning problems. Energetic reasoning is one of the propagators used to enforce this constraint. However, not much has been done to explore strategies for gen
...
Currently explanations for the Not-First/Not-Last propagators for the disjunctive constraint have not been explored thoroughly, and have room for improvement.
In this paper, we look into attempting to give more general explanations by looking through the powerset of tasks and ...
In this paper, we look into attempting to give more general explanations by looking through the powerset of tasks and ...
Explanations have been shown to significantly increase the performance of propagators, when applied to solvers that make use of Lazy Clause Generation. However, to date, there has been little work in exploring explanations for the disjunctive constraint and how they perform compa
...
Core-guided search has been prevalent in the field of Maximum Satisfiability (MaxSAT), largely due to the application of additional techniques that improve performance. With core-guided search being recently applied to Constraint Programming (CP), the question emerges whether suc
...
This paper looks at the different parts of the Critical Path and Resource Utilization (CPRU) heuristic for use in the Resource Constraint Project Scheduling Problem, with variable resources (RCPSP-t programming problem). RCPSP-t has many real-world instances such as in hospitals
...
A heuristic-guided constraint programming approach to PRCPSP-ST
Using priority-rules to guide constraint solvers
This paper introduces a new approach to the Preemptive Resource Constrained Project Scheduling Problem with setup times. The method makes use of a Constraint Optimization Problem solver, which has been modified to use priority-rule-based heuristics in its variable and value selec
...