Governing Phase I: time in the two-phase approach for Dutch infrastructure projects
Towards a predictable phase I in Dutch two-phase infrastructure Projects
The Dutch civil infrastructure stock is ageing, and the associated replacement and renovation task, estimated at some €260 billion, must be delivered more predictably and efficiently than before. As public procurement shifted from traditional Design–Bid–Build towards integrated contracts, rising tender costs and a steady decline in the number of bidders on the largest, highest-risk projects raised the prospect of weak, single-bidder competition. In response, Rijkswaterstaat (RWS) introduced the two-phase approach in 2019, in which client and contractor jointly develop the design, risk allocation and price during Phase I before execution begins in Phase II on a more realistic, market-based price. In practice, however, Phase I frequently runs longer than planned and is widely experienced as difficult to control, and existing research on delay in the design and planning stages, developed in traditional contractual settings, does not address the two phase approach. This thesis therefore asks how clients and contractors can govern time in the first phase of the two-phase approach.
The literature is drawn together into an alignment framework: structural complexity, the fixed and knowable arrangement of components, suits a predict-and-control (Type I) approach, whereas dynamic complexity, the emergent and changing relations among components, calls for a prepare-and-commit (Type II) approach. A misalignment between the two is expected to hinder time management and the predictability of the phase. Two completed or sufficiently advanced Phase I trajectories were studied, the A27 Houten–Hooipolder Noord (Case A) and the OVT 2 terminal at Zuidasdok (Case B), each through a structured assessment of Technical, Organisational and External (TOE) complexity and thirteen semi-structured interviews across client and contractor sides, with the contractor Mobilis as the main point of entry. Six resulting suggestions were then validated in a focus group with two independent RWS practitioners.
The two cases produced markedly different trajectories, and the comparison indicates that the operative variable is not the contract form but the presence or absence of deliberate counter-arrangements: where a Type II arrangement was put in place to hold control and interaction together for each pocket of dynamic complexity, complexity was contained. Where it was absent, it was free to convert into mistrust and delay. Alignment is therefore achieved or missed process by process rather than at the level of the project as a whole, and “time overrun” proved broader than mere calendar slippage. The practical leverage lies less in the choice of contract form than in the conscious, process-by-process construction of counter-arrangements that hold control and interaction together where dynamic complexity arises.
...
The literature is drawn together into an alignment framework: structural complexity, the fixed and knowable arrangement of components, suits a predict-and-control (Type I) approach, whereas dynamic complexity, the emergent and changing relations among components, calls for a prepare-and-commit (Type II) approach. A misalignment between the two is expected to hinder time management and the predictability of the phase. Two completed or sufficiently advanced Phase I trajectories were studied, the A27 Houten–Hooipolder Noord (Case A) and the OVT 2 terminal at Zuidasdok (Case B), each through a structured assessment of Technical, Organisational and External (TOE) complexity and thirteen semi-structured interviews across client and contractor sides, with the contractor Mobilis as the main point of entry. Six resulting suggestions were then validated in a focus group with two independent RWS practitioners.
The two cases produced markedly different trajectories, and the comparison indicates that the operative variable is not the contract form but the presence or absence of deliberate counter-arrangements: where a Type II arrangement was put in place to hold control and interaction together for each pocket of dynamic complexity, complexity was contained. Where it was absent, it was free to convert into mistrust and delay. Alignment is therefore achieved or missed process by process rather than at the level of the project as a whole, and “time overrun” proved broader than mere calendar slippage. The practical leverage lies less in the choice of contract form than in the conscious, process-by-process construction of counter-arrangements that hold control and interaction together where dynamic complexity arises.
...
The Dutch civil infrastructure stock is ageing, and the associated replacement and renovation task, estimated at some €260 billion, must be delivered more predictably and efficiently than before. As public procurement shifted from traditional Design–Bid–Build towards integrated contracts, rising tender costs and a steady decline in the number of bidders on the largest, highest-risk projects raised the prospect of weak, single-bidder competition. In response, Rijkswaterstaat (RWS) introduced the two-phase approach in 2019, in which client and contractor jointly develop the design, risk allocation and price during Phase I before execution begins in Phase II on a more realistic, market-based price. In practice, however, Phase I frequently runs longer than planned and is widely experienced as difficult to control, and existing research on delay in the design and planning stages, developed in traditional contractual settings, does not address the two phase approach. This thesis therefore asks how clients and contractors can govern time in the first phase of the two-phase approach.
The literature is drawn together into an alignment framework: structural complexity, the fixed and knowable arrangement of components, suits a predict-and-control (Type I) approach, whereas dynamic complexity, the emergent and changing relations among components, calls for a prepare-and-commit (Type II) approach. A misalignment between the two is expected to hinder time management and the predictability of the phase. Two completed or sufficiently advanced Phase I trajectories were studied, the A27 Houten–Hooipolder Noord (Case A) and the OVT 2 terminal at Zuidasdok (Case B), each through a structured assessment of Technical, Organisational and External (TOE) complexity and thirteen semi-structured interviews across client and contractor sides, with the contractor Mobilis as the main point of entry. Six resulting suggestions were then validated in a focus group with two independent RWS practitioners.
The two cases produced markedly different trajectories, and the comparison indicates that the operative variable is not the contract form but the presence or absence of deliberate counter-arrangements: where a Type II arrangement was put in place to hold control and interaction together for each pocket of dynamic complexity, complexity was contained. Where it was absent, it was free to convert into mistrust and delay. Alignment is therefore achieved or missed process by process rather than at the level of the project as a whole, and “time overrun” proved broader than mere calendar slippage. The practical leverage lies less in the choice of contract form than in the conscious, process-by-process construction of counter-arrangements that hold control and interaction together where dynamic complexity arises.
The literature is drawn together into an alignment framework: structural complexity, the fixed and knowable arrangement of components, suits a predict-and-control (Type I) approach, whereas dynamic complexity, the emergent and changing relations among components, calls for a prepare-and-commit (Type II) approach. A misalignment between the two is expected to hinder time management and the predictability of the phase. Two completed or sufficiently advanced Phase I trajectories were studied, the A27 Houten–Hooipolder Noord (Case A) and the OVT 2 terminal at Zuidasdok (Case B), each through a structured assessment of Technical, Organisational and External (TOE) complexity and thirteen semi-structured interviews across client and contractor sides, with the contractor Mobilis as the main point of entry. Six resulting suggestions were then validated in a focus group with two independent RWS practitioners.
The two cases produced markedly different trajectories, and the comparison indicates that the operative variable is not the contract form but the presence or absence of deliberate counter-arrangements: where a Type II arrangement was put in place to hold control and interaction together for each pocket of dynamic complexity, complexity was contained. Where it was absent, it was free to convert into mistrust and delay. Alignment is therefore achieved or missed process by process rather than at the level of the project as a whole, and “time overrun” proved broader than mere calendar slippage. The practical leverage lies less in the choice of contract form than in the conscious, process-by-process construction of counter-arrangements that hold control and interaction together where dynamic complexity arises.