The balancing act
How public construction clients safeguard public values in a changing construction industry
Early Contractor Involvement in the Netherlands
The potential of ECI in public construction projects
To implement ECI in the Dutch public construction industry, this research found several conditions to implement and use ECI. Firstly, the role division of the client, design firm and contractor should be done differently. Secondly, the distribution of the risks must change. And thirdly, procurement may have to be specifically designed for ECI. In addition to these conditions, there are three barriers to overcome. These barriers are primarily concerned with the client side of the market. The client fears the early commitment to just one contractor and finds it hard to secure the competition in the market properly when ECI is used. Following these two barriers is a third; there is a lack of determination to experiment and implement ECI. To help overcome these barriers, four incentives are identified to be applied simultaneously:
• An investment from the public sector to experiment with ECI,
• Design of a proper exit-clause to terminate the contract,
• The use of Past-Performance criteria for procuring projects with ECI,
• The application of incentives on contractor behavior.
When ECI is implemented in public construction in the Netherlands, ECI will have implications on both public construction projects and the construction industry. In procurement the criteria other than price are likely to become more important, as price is unrealistic to test on so early in a project. Contractors will have to develop their advising role and expand their designing/engineering capacity. As their expertise and capabilities develop, design and engineering work is likely to flow from the design firms to the contractors. The engineering expertise of the client must expand as well, to be able to communicate on the same level as the contractors to prevent communication errors and opportunistic behavior.
This research suggests that ECI can indeed improve public projects on several aspects, but if there are too few experiments to develop and improve the concept it is unlikely to see implementation soon. As communication, perseverance and determination are key in experimenting with something new, this thesis advocates investing in ECI experiments with people who are capable and willing to try to make ECI work. Proper preparation and learning from the experiments will create forward momentum. When forward momentum is gained, ECI could be disproved to work or be proved a working innovation in the construction market, marking the next market improvement on the road to collaboration in the construction industry. ...
To implement ECI in the Dutch public construction industry, this research found several conditions to implement and use ECI. Firstly, the role division of the client, design firm and contractor should be done differently. Secondly, the distribution of the risks must change. And thirdly, procurement may have to be specifically designed for ECI. In addition to these conditions, there are three barriers to overcome. These barriers are primarily concerned with the client side of the market. The client fears the early commitment to just one contractor and finds it hard to secure the competition in the market properly when ECI is used. Following these two barriers is a third; there is a lack of determination to experiment and implement ECI. To help overcome these barriers, four incentives are identified to be applied simultaneously:
• An investment from the public sector to experiment with ECI,
• Design of a proper exit-clause to terminate the contract,
• The use of Past-Performance criteria for procuring projects with ECI,
• The application of incentives on contractor behavior.
When ECI is implemented in public construction in the Netherlands, ECI will have implications on both public construction projects and the construction industry. In procurement the criteria other than price are likely to become more important, as price is unrealistic to test on so early in a project. Contractors will have to develop their advising role and expand their designing/engineering capacity. As their expertise and capabilities develop, design and engineering work is likely to flow from the design firms to the contractors. The engineering expertise of the client must expand as well, to be able to communicate on the same level as the contractors to prevent communication errors and opportunistic behavior.
This research suggests that ECI can indeed improve public projects on several aspects, but if there are too few experiments to develop and improve the concept it is unlikely to see implementation soon. As communication, perseverance and determination are key in experimenting with something new, this thesis advocates investing in ECI experiments with people who are capable and willing to try to make ECI work. Proper preparation and learning from the experiments will create forward momentum. When forward momentum is gained, ECI could be disproved to work or be proved a working innovation in the construction market, marking the next market improvement on the road to collaboration in the construction industry.
Creating line-of-sight in performance management
A search for and application of a practical method for brownfield asset management organisations
Adopting circular innovative technologies in the construction supply chain of the MRA
Supply Chain through the lenses of the service dominant logic’s foundational premises
Conflicts in Best Value
A research into the causes of conflicts in the execution phase of Best Value projects and what actions to take to prevent them
Open for business
Project-specific value capture strategies of architectural firms
Trust and Contractual Governance
Managing Relationships in the Offshore Industry
Capture and storage of performance information
How contractors in the water construction industry can capture and store performance information to present in Best Value tenders