“How to adapt Earned Value Management to various levels of projects based on the project complexity?”
To answer this question, the study will first outline significant aspects within EVM and assess the maturity level of organizations implementing EVM. Van Oord is chosen as the study location to gather data on their EVM application. The study then delves into potential adaptations of EVM and its effective application across diverse project types.
The research yields several significant outcomes. Firstly, the core EVM aspects are grouped under Earned Value Analysis, encompassing Planned Value (scope, budget, schedule), Actual Cost, and Earned Value. Project variance analysis, forecast calculations, and corrective action analysis are also recognized as critical components of EVM. The next step is understanding the organization maturity level, where this study reveals that EVM partially implemented in the organization and only in selected projects, following the threshold of EVM Maturity Level standards.
The next step involves the formulation of frameworks. The ABCD EVM Framework is developed based on the modified EVM 10-step model, focusing on elements such as Earned Value Analysis and the ANSI/EIA-748 standard as modified EVM components. One impactful aspect, as per the ANSI/EIA-748 Standard, involves determining the Work Breakdown Structure level, influencing the level of detail in schedule planning, budgeting, and progress tracking. Additionally, other variations include frequency of variance calculation and project forecast estimation. Various other aspects such as changes, responsibilities, reporting, and organizational decisions outlined in the discussion chapter are also differ on each project levels.
Moreover, the EVM framework is generated through TOE complexity analysis. Out of the 47 TOE Elements, 29 elements are being identified as influencing elements for the implementation of Earned Value Management. By adhering to the scalability factor from the ANSI/EIA-748 Standard and considering interview outcomes, several suggestions are formulated for Earned Value Management activities. The objective is to anticipate the high-scoring TOE elements for each project. The EVM aspects influencing this framework mainly concern the Project Measurement Baseline Plan, Budget and Schedule Authorization, the level of detail in the Work Breakdown Structure, and the recording of allocation and management reports.
Conclusively, variation in the adaptability of Earned Value Management are shown in the resulted frameworks for variety of project levels, as well as becoming tools to improve the organization maturity level. For practical application, this study recommends organization to implement EVM using the ABCD project classification or similar project sizing measurement approach while integrating insights from the TOE EVM Framework. This holistic strategy can enhance project monitoring and control across various complexity levels, contributing to the successful and effective outcomes of projects in the construction industry. ...
“How to adapt Earned Value Management to various levels of projects based on the project complexity?”
To answer this question, the study will first outline significant aspects within EVM and assess the maturity level of organizations implementing EVM. Van Oord is chosen as the study location to gather data on their EVM application. The study then delves into potential adaptations of EVM and its effective application across diverse project types.
The research yields several significant outcomes. Firstly, the core EVM aspects are grouped under Earned Value Analysis, encompassing Planned Value (scope, budget, schedule), Actual Cost, and Earned Value. Project variance analysis, forecast calculations, and corrective action analysis are also recognized as critical components of EVM. The next step is understanding the organization maturity level, where this study reveals that EVM partially implemented in the organization and only in selected projects, following the threshold of EVM Maturity Level standards.
The next step involves the formulation of frameworks. The ABCD EVM Framework is developed based on the modified EVM 10-step model, focusing on elements such as Earned Value Analysis and the ANSI/EIA-748 standard as modified EVM components. One impactful aspect, as per the ANSI/EIA-748 Standard, involves determining the Work Breakdown Structure level, influencing the level of detail in schedule planning, budgeting, and progress tracking. Additionally, other variations include frequency of variance calculation and project forecast estimation. Various other aspects such as changes, responsibilities, reporting, and organizational decisions outlined in the discussion chapter are also differ on each project levels.
Moreover, the EVM framework is generated through TOE complexity analysis. Out of the 47 TOE Elements, 29 elements are being identified as influencing elements for the implementation of Earned Value Management. By adhering to the scalability factor from the ANSI/EIA-748 Standard and considering interview outcomes, several suggestions are formulated for Earned Value Management activities. The objective is to anticipate the high-scoring TOE elements for each project. The EVM aspects influencing this framework mainly concern the Project Measurement Baseline Plan, Budget and Schedule Authorization, the level of detail in the Work Breakdown Structure, and the recording of allocation and management reports.
Conclusively, variation in the adaptability of Earned Value Management are shown in the resulted frameworks for variety of project levels, as well as becoming tools to improve the organization maturity level. For practical application, this study recommends organization to implement EVM using the ABCD project classification or similar project sizing measurement approach while integrating insights from the TOE EVM Framework. This holistic strategy can enhance project monitoring and control across various complexity levels, contributing to the successful and effective outcomes of projects in the construction industry.
The goal of this study is to provide new insights for actors in the housing construction chain, the government and science. To gain these new insights, the following research question has been formulated: How can the collaboration between actors in the Dutch housing construction industry be improved in the pursuit of sustainable supply chain management? This research was conducted through an in-depth case study research, based on literature research and semi-structured interviews with representatives from the most influential actor types in the Dutch housing construction supply chain. The housing construction supply chain contains a wide variety of actors with key players herein being main contractors, property developers and so-called first tier subcontractors
During the analysis of the interview results, an extensive amount of barriers and drivers were uncovered that actors encounter during the implementation of SSCM in the Dutch housing construction industry. For both barriers and drivers, it was found that subcontractors and property developers focus on the market and networking category, indicating they look more at the supply chain compared to main contractors. For main contractors, it seems they focus more on regulations, institutional barriers and drivers from within their own organization.
Based on the identified barriers and drivers, the following practical recommendations can accelerate the transition to SSCM in the Dutch housing construction industry. First, share knowledge with all actors in the supply chain. Second, develop a sustainable corporate culture that is reinforced both top-down and bottom-up in the organization. Third, some investments in sustainable operations are too high for a single actor to realize. Therefore, it is recommended that supply chain actors find effective ways to share financial burdens with each other in housing projects. Fourth and last, governmental institutions draft long term visions for the environment and subsequently translate this into policy.
The research findings can be used to inform and motivate main contractors, subcontractors, property developers and governments about practical implications and the use of policy instruments to achieve a sustainable supply chain in the Dutch housing construction industry. The combination of more intrinsic motivation from all actors in the housing construction chain can pave the way for creating a sustainable way of constructing houses.
...
The goal of this study is to provide new insights for actors in the housing construction chain, the government and science. To gain these new insights, the following research question has been formulated: How can the collaboration between actors in the Dutch housing construction industry be improved in the pursuit of sustainable supply chain management? This research was conducted through an in-depth case study research, based on literature research and semi-structured interviews with representatives from the most influential actor types in the Dutch housing construction supply chain. The housing construction supply chain contains a wide variety of actors with key players herein being main contractors, property developers and so-called first tier subcontractors
During the analysis of the interview results, an extensive amount of barriers and drivers were uncovered that actors encounter during the implementation of SSCM in the Dutch housing construction industry. For both barriers and drivers, it was found that subcontractors and property developers focus on the market and networking category, indicating they look more at the supply chain compared to main contractors. For main contractors, it seems they focus more on regulations, institutional barriers and drivers from within their own organization.
Based on the identified barriers and drivers, the following practical recommendations can accelerate the transition to SSCM in the Dutch housing construction industry. First, share knowledge with all actors in the supply chain. Second, develop a sustainable corporate culture that is reinforced both top-down and bottom-up in the organization. Third, some investments in sustainable operations are too high for a single actor to realize. Therefore, it is recommended that supply chain actors find effective ways to share financial burdens with each other in housing projects. Fourth and last, governmental institutions draft long term visions for the environment and subsequently translate this into policy.
The research findings can be used to inform and motivate main contractors, subcontractors, property developers and governments about practical implications and the use of policy instruments to achieve a sustainable supply chain in the Dutch housing construction industry. The combination of more intrinsic motivation from all actors in the housing construction chain can pave the way for creating a sustainable way of constructing houses.
Risk Management in Green Retrofit Projects
Eco Uncertainties
The study advocates for an integrated approach utilizing Building Information Modelling (BIM) to enhance risk management and project outcomes. It highlights the gap in current risk management practices that fail to fully address sustainability challenges in retrofits and suggests future research directions, including broader studies involving multiple companies and technologies, to develop more comprehensive risk management strategies for green retrofit projects.
...
The study advocates for an integrated approach utilizing Building Information Modelling (BIM) to enhance risk management and project outcomes. It highlights the gap in current risk management practices that fail to fully address sustainability challenges in retrofits and suggests future research directions, including broader studies involving multiple companies and technologies, to develop more comprehensive risk management strategies for green retrofit projects.
5D-based estimation of indirect construction costs
Development of an adaptive automation tool for improved efficiency of the ABK estimation process
At the same time, Building Information Models (BIM), which are increasingly used, offer an effective platform for linking data regarding construction costs. The fifth dimension of BIM in particular adds cost information to the 3D construction model. Full interoperability between the various information models is still a goal that has not been reached yet within the construction sector. Recent studies have examined inefficiencies caused by inadequate interoperability, like manual re-entry of data and duplication of tasks.
This research aims to positively contribute to the efficiency of the indirect cost estimation process by developing a 5D computer-based tool. The development of the tool was based on literature review and interviews with practitioners. Features of BIM applications were used and linked to the outcome of the indirect cost estimate. The tool was able to reduce manual interventions and reduce task durations, which resulted in a positive contribution to the efficiency of the indirect cost estimation process. Main benefits of the tool were hereby the structured guidelines for quantity take-offs, a reduction in manual intervention and time for QTO tasks and implementation of project changes within the outcome of the ABK estimate.
...
At the same time, Building Information Models (BIM), which are increasingly used, offer an effective platform for linking data regarding construction costs. The fifth dimension of BIM in particular adds cost information to the 3D construction model. Full interoperability between the various information models is still a goal that has not been reached yet within the construction sector. Recent studies have examined inefficiencies caused by inadequate interoperability, like manual re-entry of data and duplication of tasks.
This research aims to positively contribute to the efficiency of the indirect cost estimation process by developing a 5D computer-based tool. The development of the tool was based on literature review and interviews with practitioners. Features of BIM applications were used and linked to the outcome of the indirect cost estimate. The tool was able to reduce manual interventions and reduce task durations, which resulted in a positive contribution to the efficiency of the indirect cost estimation process. Main benefits of the tool were hereby the structured guidelines for quantity take-offs, a reduction in manual intervention and time for QTO tasks and implementation of project changes within the outcome of the ABK estimate.
Literature review and interviews with Janssen de Jong, a precasting concrete factory, a windows and frames supplier and an installation technology supplier revealed the large batch size of batch-and-queue manufacturing method, as the main quantifiable source of long manufacturing time, affecting significantly the delivery of sub-components and so, extending their lead time. Batch-and-queue utilizes the equipment to its maximum capacity, yet leads to stock creation at each production step. On the contrary, one-piece-flow manufacturing method (batch size of one), was indicated as a value-adding process worth to approach, yet not easily achievable, not so efficient and more expensive. One-piece-flow refers to moving the product step-by-step through each process step without non-value-added time. The conflicting interests of the suppliers and Janssen de Jong call for solutions that could satisfy both time- and cost-related interests.
The mathematical optimization model was built based on the identified conflicting relation between reducing costs and shortening lead times, in relation to the batch size. This was done considering the arguments in favor of and against both manufacturing methods. In this way, the bias is reduced. Weights are assigned to each of the objectives, denoting their relative importance to the client. A set of optimal lead times and costs is obtained, after running the model for each supplier separately, enabling Janssen de Jong to improve the project performance as per the priorities each time.
A project of 23 precast concrete houses was utilized as a case study for the model validation. Out of the involved suppliers, only the windows and frames supplier made some data accessible. This supplier already follows one-piece-flow. Access to financial data was restricted, so, a supplementary Greek company, which is active in the same field and it is highly representative of the case, was utilized. The developed model yields reasonable results compared to the real figures.
Concluding, the model proves to be effective in optimizing sub-components’ lead time in precast concrete house-building industry. However, it is recommended the model to be validated using companies from other fields (e.g. installation technology company) and incorporate further information in a future version –complex to include this in the current thesis– to achieve even higher levels of realism and applicability.
...
Literature review and interviews with Janssen de Jong, a precasting concrete factory, a windows and frames supplier and an installation technology supplier revealed the large batch size of batch-and-queue manufacturing method, as the main quantifiable source of long manufacturing time, affecting significantly the delivery of sub-components and so, extending their lead time. Batch-and-queue utilizes the equipment to its maximum capacity, yet leads to stock creation at each production step. On the contrary, one-piece-flow manufacturing method (batch size of one), was indicated as a value-adding process worth to approach, yet not easily achievable, not so efficient and more expensive. One-piece-flow refers to moving the product step-by-step through each process step without non-value-added time. The conflicting interests of the suppliers and Janssen de Jong call for solutions that could satisfy both time- and cost-related interests.
The mathematical optimization model was built based on the identified conflicting relation between reducing costs and shortening lead times, in relation to the batch size. This was done considering the arguments in favor of and against both manufacturing methods. In this way, the bias is reduced. Weights are assigned to each of the objectives, denoting their relative importance to the client. A set of optimal lead times and costs is obtained, after running the model for each supplier separately, enabling Janssen de Jong to improve the project performance as per the priorities each time.
A project of 23 precast concrete houses was utilized as a case study for the model validation. Out of the involved suppliers, only the windows and frames supplier made some data accessible. This supplier already follows one-piece-flow. Access to financial data was restricted, so, a supplementary Greek company, which is active in the same field and it is highly representative of the case, was utilized. The developed model yields reasonable results compared to the real figures.
Concluding, the model proves to be effective in optimizing sub-components’ lead time in precast concrete house-building industry. However, it is recommended the model to be validated using companies from other fields (e.g. installation technology company) and incorporate further information in a future version –complex to include this in the current thesis– to achieve even higher levels of realism and applicability.
Roadmapping the development of a green hydrogen industrial port complex
A case study in an Icelandic setting
Hydrogen generation as a means of energy distribution and storage is argued to be a viable solution to this challenge because this flexible energy carrier can be produced by any energy source and can be converted into various energy forms. The energy carrier is believed to be critical for decarbonising heavy industries, heating, and transportation.
Although hydrogen can be produced from a variety of energy sources, the only long-term key to facilitating the energy transition and establishing a new green economy would be through the electrolysis of water, fueled by renewable energy. To be economically viable, the energy would have to be provided at a large scale and at a competitive price. This makes it a global endeavour, requiring cross-border collaboration to create international supply chains.
With its potential to generate an abundance of wind energy, geothermal energy, and hydropower, Iceland is exploring its opportunity to produce hydrogen for its domestic markets and export markets. Therefore, this research is taking the Icelandic situation as a case study.
A lack of infrastructure to create, store, and transport hydrogen in significant amounts is one of the obstacles to developing the hydrogen economy. Infrastructure development needs effective coordination and substantial expenditures. In this sense, port authorities play a crucial role in bringing together all the relevant parties in the supply chain. However, creating a long-term plan to convince investors and other decision-makers presents a hurdle. The creation of a port master plan is constrained by numerous uncertainties, limited technological knowledge, and unknown social needs. There is a need for strategically roadmapping the port development process and thus structuring the decision-making process. So far, no hydrogen industrial port complex has been built and no studies have been performed about systematic thinking for the purpose of generating the possible pathways to develop such a system.
Through a single-case and practice-oriented design research methods, this research performs a SWOT analysis to determine influencing factors in developing a hydrogen industrial port complex in Iceland. This leads to the creation of an eight-phase Integrated Hydrogen Port Development-framework to narrow the knowledge gap as described above. Ultimately, this research also describes a narrative that describes practical recommendations for the Fjarðabyggð port master plan.
...
Hydrogen generation as a means of energy distribution and storage is argued to be a viable solution to this challenge because this flexible energy carrier can be produced by any energy source and can be converted into various energy forms. The energy carrier is believed to be critical for decarbonising heavy industries, heating, and transportation.
Although hydrogen can be produced from a variety of energy sources, the only long-term key to facilitating the energy transition and establishing a new green economy would be through the electrolysis of water, fueled by renewable energy. To be economically viable, the energy would have to be provided at a large scale and at a competitive price. This makes it a global endeavour, requiring cross-border collaboration to create international supply chains.
With its potential to generate an abundance of wind energy, geothermal energy, and hydropower, Iceland is exploring its opportunity to produce hydrogen for its domestic markets and export markets. Therefore, this research is taking the Icelandic situation as a case study.
A lack of infrastructure to create, store, and transport hydrogen in significant amounts is one of the obstacles to developing the hydrogen economy. Infrastructure development needs effective coordination and substantial expenditures. In this sense, port authorities play a crucial role in bringing together all the relevant parties in the supply chain. However, creating a long-term plan to convince investors and other decision-makers presents a hurdle. The creation of a port master plan is constrained by numerous uncertainties, limited technological knowledge, and unknown social needs. There is a need for strategically roadmapping the port development process and thus structuring the decision-making process. So far, no hydrogen industrial port complex has been built and no studies have been performed about systematic thinking for the purpose of generating the possible pathways to develop such a system.
Through a single-case and practice-oriented design research methods, this research performs a SWOT analysis to determine influencing factors in developing a hydrogen industrial port complex in Iceland. This leads to the creation of an eight-phase Integrated Hydrogen Port Development-framework to narrow the knowledge gap as described above. Ultimately, this research also describes a narrative that describes practical recommendations for the Fjarðabyggð port master plan.
...
Towards data-driven project planning
Exploring the possibilities of generation and implementation of throughput times based on data analysis
Tender Price Predictor
Predicting Tender Prices of Dutch Infrastructure Projects with Machine Learning
Machine Learning has been a popular method in various industries to predict future outcomes and uncover patterns in historical data but remains a rather novel phenomenon in the construction industry. Machine Learning models have been developed in the past to aid tender management, but not with a focus on predicting the contractor’s tender price.
The objective of this research is to develop a Machine Learning tool that is able to predict the tender price of infrastructure projects accurately and is able to assist the contractor’s tender professionals in their decision to tender.
In order to achieve this objective, the following research question was formulated:
How can a Machine Learning algorithm, predicting the tender’s price using tender project data, be developed to support the contractor’s decision to tender?
First, a literature study is conducted to explore the state-of-the-art developments of Machine Learning within construction tender management, discover what the most popular regression algorithms are and what the most important tender features are that influence the tender price. Based on the most important tender features and interviews with tender professionals of a Dutch contractor, an extensive list of 93 tender features is filtered until a final set of tender features remains. Data on these tender features are collected in order to be used as input for the Machine Learning model.
The SVR model performed the best with an R-Squared of 0.846, implying that 84.6% of the variance of the tender’s price could be explained by the model. The SVR model includes an optimised set of features, which is a subset of the initial dataset. The initial estimate is considered to be significantly more important than the other features.
In order to implement the Tender Price Predictor in the organization of a Dutch contractor, attention should be paid to the required effort of the users and to ensuring a high quality of tender data. Requiring too much effort from tender managers entering the input data into the database may result in worse quality of data. Both the users of the model and the managers submitting tender data should be trained accordingly in order to obtain maximum effectiveness.
It should be noted that some important features, according to practice and literature, are omitted from the final dataset. Although the final set of features complies with the requirements of generic features and sufficient occurrences in either literature or the interviews, they were not present in the database of the contractor. These omitted features are: ‘Project team experience’ and ‘Location’ ...
Machine Learning has been a popular method in various industries to predict future outcomes and uncover patterns in historical data but remains a rather novel phenomenon in the construction industry. Machine Learning models have been developed in the past to aid tender management, but not with a focus on predicting the contractor’s tender price.
The objective of this research is to develop a Machine Learning tool that is able to predict the tender price of infrastructure projects accurately and is able to assist the contractor’s tender professionals in their decision to tender.
In order to achieve this objective, the following research question was formulated:
How can a Machine Learning algorithm, predicting the tender’s price using tender project data, be developed to support the contractor’s decision to tender?
First, a literature study is conducted to explore the state-of-the-art developments of Machine Learning within construction tender management, discover what the most popular regression algorithms are and what the most important tender features are that influence the tender price. Based on the most important tender features and interviews with tender professionals of a Dutch contractor, an extensive list of 93 tender features is filtered until a final set of tender features remains. Data on these tender features are collected in order to be used as input for the Machine Learning model.
The SVR model performed the best with an R-Squared of 0.846, implying that 84.6% of the variance of the tender’s price could be explained by the model. The SVR model includes an optimised set of features, which is a subset of the initial dataset. The initial estimate is considered to be significantly more important than the other features.
In order to implement the Tender Price Predictor in the organization of a Dutch contractor, attention should be paid to the required effort of the users and to ensuring a high quality of tender data. Requiring too much effort from tender managers entering the input data into the database may result in worse quality of data. Both the users of the model and the managers submitting tender data should be trained accordingly in order to obtain maximum effectiveness.
It should be noted that some important features, according to practice and literature, are omitted from the final dataset. Although the final set of features complies with the requirements of generic features and sufficient occurrences in either literature or the interviews, they were not present in the database of the contractor. These omitted features are: ‘Project team experience’ and ‘Location’
Trust in inter-organizational construction design teams: The effect of interpersonal ties and the moderating role of virtual meetings
Developing a guideline to improve trust via prior and future ties
Data-Driven Decision-Making for Circular Building Design
Development of an automated decision-support framework for an improved circular design workflow
Early Warning Signs in Risk Management
Improve Accuracy of Cost Contingency by Implementing Early Warning signs in Risk Management to prevent Cost Overruns
During the execution phase projects are monitored with performance indicators, which provide information about past events or activities. This means these indicators are lagging, hence it limits proactive project management. On the contrary, leading indicators could function as early warning signs as they present themselves before potential issues arise, or risks materialize.
The objective of this research is to improve the cost contingency process by implementing early warning signs, in order to proactively manage projects and minimise cost overruns and materialized risks. In order to achieve this objective the following main research question is formulated: “How can early warning signs be used in large construction projects to improve accuracy of cost contingency estimates and management in order to minimize cost overruns?”
Concluding from the empirical study, early warning signs can be implemented in the cost contingency process by shifting the focus of risk management from mitigating and managing the effects of risks towards the causes of risks. Subsequently, risk strategies and mitigation measures can be more effective when aimed at the origin of the issue, instead of the direct issue leading to the risk. It is valuable to examine the risks as a system or network, instead of single problems, because it provides a better representation of reality and the links between risks or other events reveal information about correlation or side effects. Consequently, mitigation measures can increase in efficiency, when one cause, leading to multiple risks, is targeted. Furthermore, materialization of a risk is detected as an early warning sign which contains information about causes or circumstances that trigger other risks as well. Additionally, the increase of a RISMAN score indicates a change in project circumstances and therefore can be used as an early warning for materialization of risks. The justification for an increase in RISMAN score is diverse, and should thus be analysed to reveal the specific information needed to prevent materialization of risks.
A common database contributes to the early warning sign approach as well, because it overcomes the in the case study identified ‘surveillance filter’, by improving collection and transfer of information. Tracking the cost contingency increases the accuracy of this estimate in general, because it provides insight into the development during project phases and the actual spending pattern. And when this info is stored in a database it allows referencing from previous projects, hence including an ‘outside view’.
...
During the execution phase projects are monitored with performance indicators, which provide information about past events or activities. This means these indicators are lagging, hence it limits proactive project management. On the contrary, leading indicators could function as early warning signs as they present themselves before potential issues arise, or risks materialize.
The objective of this research is to improve the cost contingency process by implementing early warning signs, in order to proactively manage projects and minimise cost overruns and materialized risks. In order to achieve this objective the following main research question is formulated: “How can early warning signs be used in large construction projects to improve accuracy of cost contingency estimates and management in order to minimize cost overruns?”
Concluding from the empirical study, early warning signs can be implemented in the cost contingency process by shifting the focus of risk management from mitigating and managing the effects of risks towards the causes of risks. Subsequently, risk strategies and mitigation measures can be more effective when aimed at the origin of the issue, instead of the direct issue leading to the risk. It is valuable to examine the risks as a system or network, instead of single problems, because it provides a better representation of reality and the links between risks or other events reveal information about correlation or side effects. Consequently, mitigation measures can increase in efficiency, when one cause, leading to multiple risks, is targeted. Furthermore, materialization of a risk is detected as an early warning sign which contains information about causes or circumstances that trigger other risks as well. Additionally, the increase of a RISMAN score indicates a change in project circumstances and therefore can be used as an early warning for materialization of risks. The justification for an increase in RISMAN score is diverse, and should thus be analysed to reveal the specific information needed to prevent materialization of risks.
A common database contributes to the early warning sign approach as well, because it overcomes the in the case study identified ‘surveillance filter’, by improving collection and transfer of information. Tracking the cost contingency increases the accuracy of this estimate in general, because it provides insight into the development during project phases and the actual spending pattern. And when this info is stored in a database it allows referencing from previous projects, hence including an ‘outside view’.
Integrating Sustainable Objectives in Transmission System Operators' Projects
A decision-support framework for the prioritisation and integration of sustainable objectives in projects
First, a literature study was conducted to define sustainability and the concepts associated with it. To properly understand the context of TenneT and identify the limitations associated with sustainability, company professionals were interviewed. This pointed to the need for prioritisation and gradual integration of sustainability measures. A desktop study was also conducted to identify the company’s sustainable goals, their associated measures, and their real-life applications. A decision-support framework for integrating sustainable goals in projects, based on Multi-Criteria Decision-Analysis (MCDA) was proposed. Using the Best-Worst Method (BWM), as the selected MCDA method, developed by Rezaei (2015), a sustainability workshop was organised where decision-makers from TenneT were asked to select relevant sustainability goals for TenneT, and the ones selected by three or more decision-makers were then used for performing the BWM. To avoid focusing on already well-performing sustainability goals, the performance of their associated measures was studied, using a Maturity Model based on the work of Silvius and Schipper (2015). Finally, an Importance-Performance Analysis (Martilla and James 1977) was performed, to assess future actions for each sustainable goal. The BWM showed that the Planet aspect was selected as the most important one for stimulating sustainability in projects. Additionally, Reducing Emissions was selected as the most important sub-aspect while in the People aspect, Health and Safety ranked first. The Maturity Model showed that the least integrated goals in projects are Human Rights, Labour Conditions and Decent Work, Energy Consumption, Materials and Natural Resources and Circularity and Waste. The BWM and Maturity Model also produced interesting results regarding the awareness of decision-makers and how they perceive sustainable goals and the performance of their associated measures in projects.
Based on the Importance-Performance analysis, the research suggests integrating the sustainable goal of Circularity and Waste in the company’s following projects. This can be achieved by using existing sustainable measures, such as the Raw Material Passport (RMP), in the tender process. Using measures such as the RMP in the pre-qualification phases or selection phase, as entry requirements with specific targets to be met, or as an award criterion, aiming to create added value for the project, can stimulate the contractors and suppliers to act more sustainably. This will in turn increase TenneT’s sustainable performance and will help the company meet its own sustainable targets.
...
First, a literature study was conducted to define sustainability and the concepts associated with it. To properly understand the context of TenneT and identify the limitations associated with sustainability, company professionals were interviewed. This pointed to the need for prioritisation and gradual integration of sustainability measures. A desktop study was also conducted to identify the company’s sustainable goals, their associated measures, and their real-life applications. A decision-support framework for integrating sustainable goals in projects, based on Multi-Criteria Decision-Analysis (MCDA) was proposed. Using the Best-Worst Method (BWM), as the selected MCDA method, developed by Rezaei (2015), a sustainability workshop was organised where decision-makers from TenneT were asked to select relevant sustainability goals for TenneT, and the ones selected by three or more decision-makers were then used for performing the BWM. To avoid focusing on already well-performing sustainability goals, the performance of their associated measures was studied, using a Maturity Model based on the work of Silvius and Schipper (2015). Finally, an Importance-Performance Analysis (Martilla and James 1977) was performed, to assess future actions for each sustainable goal. The BWM showed that the Planet aspect was selected as the most important one for stimulating sustainability in projects. Additionally, Reducing Emissions was selected as the most important sub-aspect while in the People aspect, Health and Safety ranked first. The Maturity Model showed that the least integrated goals in projects are Human Rights, Labour Conditions and Decent Work, Energy Consumption, Materials and Natural Resources and Circularity and Waste. The BWM and Maturity Model also produced interesting results regarding the awareness of decision-makers and how they perceive sustainable goals and the performance of their associated measures in projects.
Based on the Importance-Performance analysis, the research suggests integrating the sustainable goal of Circularity and Waste in the company’s following projects. This can be achieved by using existing sustainable measures, such as the Raw Material Passport (RMP), in the tender process. Using measures such as the RMP in the pre-qualification phases or selection phase, as entry requirements with specific targets to be met, or as an award criterion, aiming to create added value for the project, can stimulate the contractors and suppliers to act more sustainably. This will in turn increase TenneT’s sustainable performance and will help the company meet its own sustainable targets.
Grounded in Jalai Sohi (2018), the research identifies 13 enablers and strategies for flexible scope, with a strong emphasis on soft factors such as trust, stakeholder involvement, communication, collaboration, commitment, and managerial review; an additional enabler—interaction among stakeholders—is incorporated. Three enablers were selected for deeper investigation: broad task definition, embrace change, and interaction among stakeholders. Barriers to implementing these enablers were categorized as limited awareness, stakeholder-driven barriers, organizational behavior, and contractual barriers, informing the development of a practical framework.
Value Engineering (VE) is examined as a complementary approach. VE is a structured process aimed at achieving essential functions at the lowest life-cycle cost while increasing project value, extending beyond mere cost cutting. Although evidence for VE in construction remains limited, the study identifies 21 potential benefits and validates them via a practitioner survey (n=25), with all benefits scoring a Relative Importance Index above 0.6.
Two case studies illustrate VE and enabler implementation. In Case 1, VE was introduced after scope development, leading to stakeholder resistance; in Case 2, VE was used proactively from the outset, yielding earlier consensus and fewer barriers. The most common barrier observed is lack of trust. A framework is proposed to resolve barriers by spreading awareness of enablers, ensuring stakeholder engagement, and conducting VE, supported by expert analysis. The findings suggest VE and soft-factor enablers can enhance scope flexibility, though broader empirical validation is recommended. ...
Grounded in Jalai Sohi (2018), the research identifies 13 enablers and strategies for flexible scope, with a strong emphasis on soft factors such as trust, stakeholder involvement, communication, collaboration, commitment, and managerial review; an additional enabler—interaction among stakeholders—is incorporated. Three enablers were selected for deeper investigation: broad task definition, embrace change, and interaction among stakeholders. Barriers to implementing these enablers were categorized as limited awareness, stakeholder-driven barriers, organizational behavior, and contractual barriers, informing the development of a practical framework.
Value Engineering (VE) is examined as a complementary approach. VE is a structured process aimed at achieving essential functions at the lowest life-cycle cost while increasing project value, extending beyond mere cost cutting. Although evidence for VE in construction remains limited, the study identifies 21 potential benefits and validates them via a practitioner survey (n=25), with all benefits scoring a Relative Importance Index above 0.6.
Two case studies illustrate VE and enabler implementation. In Case 1, VE was introduced after scope development, leading to stakeholder resistance; in Case 2, VE was used proactively from the outset, yielding earlier consensus and fewer barriers. The most common barrier observed is lack of trust. A framework is proposed to resolve barriers by spreading awareness of enablers, ensuring stakeholder engagement, and conducting VE, supported by expert analysis. The findings suggest VE and soft-factor enablers can enhance scope flexibility, though broader empirical validation is recommended.
Green Public Procurement in the Dutch Construction Sector
A qualitative research on the inclusion of environmental requirements in procurement of construction projects
Towards 5D BIM
A Process Map for Effective Design and Cost Estimation Integration
To answer the research question, several steps were performed. From the case study research, the following issues on fragmentation and BIM application are identified: [1] unsteady involvement of the cost engineer in the design, [2] limited influence of the cost engineer on the design, [3] model complexity, [4] incompatibility of model information and cost estimation, [5] absence of standardized and uniform information representation, and [6] resistance of clients and practitioners to the application of BIM/5D BIM.
By countering these issues, the “Integrated Design – Cost Estimation 5D BIM Process” is designed to answer the research question. The integration between design and cost estimation via 5D BIM focuses on cost driving components which are components influencing costs. Accordingly, these components are considered as key for communication, discussions between designers and cost engineers, and model development. Focusing on cost driving components, the process balances the information in the model. The information in the model is checked for compatibility with the estimate’s accuracy. Furthermore, the process proposes the consideration of the cost engineer’s perspective in the design. Then, 5D BIM is incorporated in the designed process by standardizing information and following the semi-automated approach for cost computation.
To assess the effectiveness of the integration addressed in the research question, a pilot case is performed to test the process in a running project. From the observations, it is concluded that the process provided a standard representation of objects, enhanced the communication between the designer and cost engineer, and involved the cost engineer earlier in the design. Furthermore, the pilot case led to the conclusion on barriers to BIM implementation. These include: the cultural change from individual effort to collaboration, lack of support from the management and client, inadequate planning for BIM application, and the inexperience in applying 5D BIM. These factors limited the successful implementation to reach effective integration. Despite the limited integration achieved in the pilot case, project participants and interviewed BIM experts ensured that the process leads to effective integration. However, it is crucial to respond to the noted barriers to have effective integration between designers and cost engineers via 5D BIM. ...
To answer the research question, several steps were performed. From the case study research, the following issues on fragmentation and BIM application are identified: [1] unsteady involvement of the cost engineer in the design, [2] limited influence of the cost engineer on the design, [3] model complexity, [4] incompatibility of model information and cost estimation, [5] absence of standardized and uniform information representation, and [6] resistance of clients and practitioners to the application of BIM/5D BIM.
By countering these issues, the “Integrated Design – Cost Estimation 5D BIM Process” is designed to answer the research question. The integration between design and cost estimation via 5D BIM focuses on cost driving components which are components influencing costs. Accordingly, these components are considered as key for communication, discussions between designers and cost engineers, and model development. Focusing on cost driving components, the process balances the information in the model. The information in the model is checked for compatibility with the estimate’s accuracy. Furthermore, the process proposes the consideration of the cost engineer’s perspective in the design. Then, 5D BIM is incorporated in the designed process by standardizing information and following the semi-automated approach for cost computation.
To assess the effectiveness of the integration addressed in the research question, a pilot case is performed to test the process in a running project. From the observations, it is concluded that the process provided a standard representation of objects, enhanced the communication between the designer and cost engineer, and involved the cost engineer earlier in the design. Furthermore, the pilot case led to the conclusion on barriers to BIM implementation. These include: the cultural change from individual effort to collaboration, lack of support from the management and client, inadequate planning for BIM application, and the inexperience in applying 5D BIM. These factors limited the successful implementation to reach effective integration. Despite the limited integration achieved in the pilot case, project participants and interviewed BIM experts ensured that the process leads to effective integration. However, it is crucial to respond to the noted barriers to have effective integration between designers and cost engineers via 5D BIM.
results of literature review and exploratory interviews. The purpose of the proposed conceptual model is to illustrate contractual and relational elements that can be added to the current risk sharing in order to promote cooperation. Then, the proposed risk sharing mechanisms that constitute the conceptual model are discussed with practitioners. This activity aims to refine the proposed risk sharing mechanisms in order to obtain detailed measures that form the risk sharing framework. Finally, the proposed framework is validated with experts in order to assess whether it meets the economic and functional requirements of its intended users and fits within the restrictions imposed by the current practice. The risk sharing mechanisms applied in the construction sector mentioned in the literature refer to financial incentives such as government guarantees, target cost contracts, etc. However, the literature study suggests that the attitude and willingness of partners to engage in cooperative behaviours is stimulated more by trust and relational norms than formal enforceable rules. Therefore, it can be argued that risk sharing requires additional elements in order to promote cooperation. The proposed risk sharing framework requires certain personal attitudes of team members in order to be effective in promoting cooperation. According to practitioners, partners should: • seek the participation of all team(s)members, internal and external; • take the initiative to help rather than being passive; • show behaviours oriented toward the achievement of common goals and mutual benefits; • be open and receptive to new ideas, different perspectives, external influence; Furthermore, an essential attitude is to accept and embrace the idea that risk ownership does not exclude the chance of managing a risk together. The legal boundary of having one risk owner should not prevent partners from being forthcoming and providing support to control risks. Based on the results of the discussion with practitioners, the proposed risk sharing framework is effective in stimulating cooperation only if partners coordinate with each other and commit to implement these measures together. ...
results of literature review and exploratory interviews. The purpose of the proposed conceptual model is to illustrate contractual and relational elements that can be added to the current risk sharing in order to promote cooperation. Then, the proposed risk sharing mechanisms that constitute the conceptual model are discussed with practitioners. This activity aims to refine the proposed risk sharing mechanisms in order to obtain detailed measures that form the risk sharing framework. Finally, the proposed framework is validated with experts in order to assess whether it meets the economic and functional requirements of its intended users and fits within the restrictions imposed by the current practice. The risk sharing mechanisms applied in the construction sector mentioned in the literature refer to financial incentives such as government guarantees, target cost contracts, etc. However, the literature study suggests that the attitude and willingness of partners to engage in cooperative behaviours is stimulated more by trust and relational norms than formal enforceable rules. Therefore, it can be argued that risk sharing requires additional elements in order to promote cooperation. The proposed risk sharing framework requires certain personal attitudes of team members in order to be effective in promoting cooperation. According to practitioners, partners should: • seek the participation of all team(s)members, internal and external; • take the initiative to help rather than being passive; • show behaviours oriented toward the achievement of common goals and mutual benefits; • be open and receptive to new ideas, different perspectives, external influence; Furthermore, an essential attitude is to accept and embrace the idea that risk ownership does not exclude the chance of managing a risk together. The legal boundary of having one risk owner should not prevent partners from being forthcoming and providing support to control risks. Based on the results of the discussion with practitioners, the proposed risk sharing framework is effective in stimulating cooperation only if partners coordinate with each other and commit to implement these measures together.
...